Goldsmiths, University of London, Energy Centre Upgrade
A new modular boiler plant in a sub-ground energy centre, delivered with temporary plant and zero operational downtime across the campus.

Overview
Preou completed a full energy centre upgrade at Goldsmiths, University of London, in New Cross, as part of the institution's infrastructure modernisation programme. The project involved the design, installation and commissioning of a new modular boiler plant within the lower ground floor energy centre. The new high-efficiency LTHW system has significantly improved energy performance, resilience and compliance across the campus.
Live campus delivery
A key challenge was maintaining continuous heating and hot water during the works. Preou provided a temporary boiler plant to ensure full service continuity, avoiding any disruption to academic, residential and critical buildings.
Working in a sub-ground floor plant room added complexity, requiring the removal of a ground floor louvre, specialist crane operations and careful removal and installation of plant equipment in sections.
Scope and integration
Preou managed the full turnkey delivery, including the safe removal of the legacy LTHW system and the mechanical design of the new modular plant. The installation integrated LTHW networks, natural gas, cold water mains, drainage, a compliant flue system, electrical systems and full BMS control. Final commissioning and performance testing ensured the system met all regulatory and operational standards.
Outcome
The project was delivered with zero operational downtime, enhancing energy efficiency, system resilience and control through advanced BMS integration. The result is a future-proof energy centre with improved serviceability, supporting the university's long-term sustainability goals.
Project photographs

Related case studies

Minster in Sheppey Schools
An outdated one-pipe heating system removed across the Upper and Lower Schools and replaced in an eight-week programme, with heat on in time for winter.
Read the case studyGrove Road School
Heating and mains hot and cold water systems replaced across three school buildings during the holidays, on time and within budget.
Read the case study
£700kSt Claudine's Heating Distribution
Heating and hot and cold water distribution pipework replaced in the Our Lady's Wing inside a demanding six-week holiday programme.
Read the case studyPlanning a similar project?
Send us your drawings and specification, or call the office to discuss the programme.