Minster in Sheppey, Heating Installation
An outdated one-pipe heating system removed across the Upper and Lower Schools and replaced in an eight-week programme, with heat on in time for winter.

Overview
We undertook a comprehensive heating system upgrade at Minster in Sheppey, involving the full removal of the outdated one-pipe heating system and radiators across both the Upper and Lower Schools. The project was delivered within an eight-week programme and achieved the critical target of providing treated heat in time for the start of winter.
Scope of works
A total of 95 new radiators and complete new pipework were installed throughout both school buildings. In the Upper School, the new heating system was integrated with the existing three boilers. The plant room was significantly upgraded with new pipework, a pressurisation unit, a plate heat exchanger, new primary and secondary pumps, and modified Trend controls to accommodate the new installation.
In the Lower School, the boiler room was completely stripped and refitted with two new high-efficiency boilers, a dosing pot, and new pumps and pipework. Both heating systems were fully flushed, chemically treated and commissioned.
Outcome
All exposed pipework was boxed in as part of the builders work to enhance safety and prevent pupils from coming into contact with hot surfaces. The project was delivered on time, with heating fully operational by the scheduled date.
In addition to the main contract, we carried out responsive repairs to other school boilers, including the replacement of heat exchangers and ancillary components, working directly with school management to minimise disruption.
Project photographs


Related case studies
£1.1 millionGoldsmiths Energy Centre
A new modular boiler plant in a sub-ground energy centre, delivered with temporary plant and zero operational downtime across the campus.
Read the case studyGrove Road School
Heating and mains hot and cold water systems replaced across three school buildings during the holidays, on time and within budget.
Read the case study
£700kSt Claudine's Heating Distribution
Heating and hot and cold water distribution pipework replaced in the Our Lady's Wing inside a demanding six-week holiday programme.
Read the case studyPlanning a similar project?