Laurel Park School, Heating and Radiator Replacement

A full heating and mechanical services upgrade in a live school: plant room renewal, phased radiator replacement and BMS upgrade over ten weeks.

£692,153Education10 week programmePhased radiator replacement
A Preou van outside Laurel Park School

Overview

Preou Heating Ventilation and Air Conditioning Ltd was appointed to deliver a full heating and mechanical services upgrade within a live educational facility. The works focused on removing redundant plant and distribution pipework, upgrading radiator systems across multiple heating circuits, and improving overall efficiency, control and long-term reliability.

Programme

The project was delivered across a structured ten-week programme, beginning with mobilisation, RAMS approval and permit-to-work procedures. Early works included the safe isolation and strip-out of the Tower plant room mechanical and electrical systems, removal of redundant radiators and pipework serving classrooms, and surveying of new service routes. Asbestos risks were identified and managed in accordance with statutory requirements.

Scope of works

Following strip-out, the main plant room was upgraded with new equipment including a degasser, air separator, water softener, side stream filtration and dosing units, alongside new electrical supplies and isolators. BMS upgrades ensured the new plant and systems were fully integrated and optimised.

Radiator replacement works were then completed in phases across the Tower-connected areas, System 2, the Sports Hall and finally System 1. This included new radiators, valves, balancing devices, pipework modifications and associated ceiling and boxing works, ensuring access for future maintenance. External pipework was protected with new trace heating and insulation.

Handover

Once installation was complete, the systems were flushed, cleaned and chemically dosed, followed by pressure testing, commissioning, balancing, water quality testing and full BMS commissioning. The project concluded with a full handover including O&M manuals, as-fitted drawings, commissioning results, logbook updates, staff training and final client sign-off.

Project photographs

A Preou van outside Laurel Park School
A Preou van outside Laurel Park School

Planning a similar project?

Send us your drawings and specification, or call the office to discuss the programme.

Get in touch with Preou HVAC Ltd

Tell us about the building and the plant, and a member of the team will come back to you to discuss the project in detail.

TelephoneCall us
Email 
Office8 Radford Crescent, Billericay, Essex CM12 0DU

Key contacts

  • Daniel Herold, Managing Director
  • Julia Herold, Finance Director
  • Charles Romero, Business Development

Start a project

Send drawings, a specification or a description of the plant. We reply within one working day.

We reply within one working day.