La Sainte Union Catholic School, Plant Room Upgrade

Two plant rooms refurbished and joined into one network by new underground pipework, with the school kept fully operational for six months.

£540kEducationTwo plant rooms integratedFour cascade boilers
Gauges, pumps and insulated pipework in a plant room at La Sainte Union School

Project overview

We were appointed to deliver a comprehensive upgrade of the mechanical plant and associated services at La Sainte Union School, improving system reliability, operational efficiency and long-term performance.

The project involved refurbishment works to two separate plant rooms, one located beneath the main school building and the other adjacent to the tennis courts. A key element of the scheme was the integration of both systems to operate as one coordinated and efficient network.

Scope of works

The works commenced with the full removal and disposal of existing plant equipment within both plant rooms. We then installed new underground pipework to connect the two systems, carrying out all excavation works and completing full reinstatement of the surrounding landscape.

The new installation included thirteen pumps, two low loss headers, two plate heat exchangers, one calorifier and four high-efficiency boilers installed on a cascade arrangement to improve system efficiency and resilience. We also installed new Trend BMS interface panels to provide enhanced monitoring and control of the plant.

Further works included new trace heating, bespoke flue systems and a bespoke fresh air supply system serving the boilers. The systems were fully flushed and chemically dosed, followed by comprehensive testing and commissioning, a full client demonstration and detailed record drawings.

Keeping the school open

To ensure the school remained fully operational throughout the six-month programme, we installed and maintained temporary hot water plant, allowing continuity of service with no disruption to daily operations.

Outcome

The completed project delivered a modernised and fully integrated plant system with improved reliability, enhanced energy efficiency through cascade boiler control and upgraded building management capability. The project was delivered safely, on programme and with minimal disruption within a live school environment.

Project photographs

Gauges, pumps and insulated pipework in a plant room at La Sainte Union School
Gauges, pumps and insulated pipework in a plant room at La Sainte Union School
La Sainte Union Catholic School, Highgate Road
La Sainte Union Catholic School, Highgate Road

Planning a similar project?

Send us your drawings and specification, or call the office to discuss the programme.

Get in touch with Preou HVAC Ltd

Tell us about the building and the plant, and a member of the team will come back to you to discuss the project in detail.

TelephoneCall us
Email 
Office8 Radford Crescent, Billericay, Essex CM12 0DU

Key contacts

  • Daniel Herold, Managing Director
  • Julia Herold, Finance Director
  • Charles Romero, Business Development

Start a project

Send drawings, a specification or a description of the plant. We reply within one working day.

We reply within one working day.