Goldsmiths, University of London, Great Hall Radiators
Twelve sectional steel radiators replaced in the Great Hall inside a four-day window before student examinations.

The brief
Goldsmiths required a fast-track heating upgrade in their Great Hall. The project involved the installation of 12 sectional steel radiators within an extremely tight four-day window. The hall had to be fully operational immediately after the works, as it was scheduled to host student exams.
Delivery
The Preou team coordinated closely with the university to schedule the works during a short access period. Materials were pre-checked and delivered in advance, and a dedicated team was assigned to work continuously across the four days. Our engineers managed the safe removal of old equipment, installation of the new radiators, and full testing and commissioning.
Outcome
The project was completed on time, with the Great Hall returned to the university fully heated and ready for use.
Project photographs

Related case studies

Minster in Sheppey Schools
An outdated one-pipe heating system removed across the Upper and Lower Schools and replaced in an eight-week programme, with heat on in time for winter.
Read the case study
£1.1 millionGoldsmiths Energy Centre
A new modular boiler plant in a sub-ground energy centre, delivered with temporary plant and zero operational downtime across the campus.
Read the case studyGrove Road School
Heating and mains hot and cold water systems replaced across three school buildings during the holidays, on time and within budget.
Read the case studyPlanning a similar project?
Send us your drawings and specification, or call the office to discuss the programme.