01708 755055 info@preou.co.uk
Select Page

Copenhagen School

Islington London – CEA at Islington

 

We acted as the Principal Contractor for the clients appointed consultants Beveridge Associates. We replaced the schools heating system of radiators and circulation pipe work. We also installed to the IT room Air Conditioning. These works were a major task as the building is listed as grade 2. The total value was in excess of £145K.

Special attention had to be given to planning the works to replace each wing of the building separately to avoid the need for the school to suffer complete heating shutdown. This was a challenge for our engineers and builders as in places the walls were a meter thick and we were not able to cut away the existing structure, we had to follow existing building profiles. Our works involved all the installation needs for the complete project, building works, decorations electrical works as a complete package. The works were completed on time and within budget. The school is delighted with the end result.